What prompted the need for the service? The city of Buffalo needed a secure place to put water line after it was exposed due to a recent storm.
Who were the companies involved? Turner Underground Installations (GC) City of Buffalo (client)
What were specs of the job? 16 inch diameter 1000 feet
What challenges/obstacles occurred during? 1000 feet in one shot drilling 30 feet under the water line in the canal through rock.
What was the ending outcome? Now the city of buffalo has s secure water line under that is sagre and more protected from the event of a storm.
See More Projects
Project at a Glance
Client
City of Buffalo
Job Specs
16 inch diameter 1000 feet
Installation Type
none
Equipment Used
Ditch Witch JT100.