Project Overview
What prompted the need for the service? Owner, Markwest Energy Partners proposed a project in Doddridge and Wetzel Counties in West Virginia. Their proposal includes new piping to be installed for a gas main
Who were the companies involved? Markwest Energy Partners, Design Engineer was Civil & Environmental Consultants, Inc.
What were specs of the job? Two Sites: 900 linear feet length of pipe to be drilled under US Rte. 50; 1,100 linear feet of 20-inch steel gas main in rock under US Rte.23.
What challenges/obstacles occurred during? Working alongside main highways/roadways presented a greater difficulty of work. The crews had to be extra observant and cautious when dealing with busy roadways like US Rte.50.
What was the ending outcome? now there a new gas main in WV under the highways of route 23 and route 50.